6 Mar. 2020

1,614 bytes added, 11:22, 20 March 2020
Rename from 6 Feb 2020 page
1. Mechanical design and interfaces<br/>
<li>Filter slides in detailed stages. Stuart to create a step file from the Zemax with fixed workplanes to aid referencing individual CAD assemblies.<br/>
<li>Kathryn to set up interactive cable/equipment list based on Coggle diagram received, detailing by all parties</li>
<br/>
2. Parts procurement<br/>
<li>Nikon has been received
<li>CCD has been ordered from Andor
<br/><br/>
3. Software<br/>
<li>Software working group to be formed, first meeting in the 1200 SAST time slot on 2020/03/13. Carel will invite the relevant SAAO parties.<br />
<li>Draft functionality requirements from SAAO side to be developed during the course of the week, for discussion Friday - Carel to distribute<br/>
<li>Draft capabilities and any interactive requirements from LJMU side to be developed (i.e. what commands and information do LJMU currently expect the instrument to issue)
<br/><br/>
4. Slit<br/>
<li>SAAO to discuss slit requirements<br/>
<li>LJMU manufacture these in house, so it can be any configuration<br/>
<li>Iain distributed an example multi-width slit arrangement they have in use
[[File:slit_example_iain_20200306.png|thumbnail]]
<br/>
5. Schedule and reviews<br/>
<li>A hardware design review is required to push forward on manufacturing - target end March<br/>
<li>Durations estimates from LJMU:<br/>
<li>From design review ~ 2 months for hardware manufacture<br/>
<li>From manufacture ~ 2 months for setup and lab testing<br/>
<li>Software effort unknown at this stage<br/>
<li>Area on wiki to be set up with FAT topics & prelim delivery placeholders (Kathryn)<br/>