transients (with ToO override capability)
'''Schedule:'''
Preliminary building design: completed Nov 2019
Ash Dome (9-m diameter): arrival at Sutherland expected end Mar 2020
Building commencement expected: end-April 2020
Building completion expected: end-Sep 2020
Telescope and dome installation: Oct 2020
Camera completion: end 2020
Commissioning: beginning early 2021
'''SAAO Contact:'''
David Buckley (PM)