1. Mechanical design and interfaces
+
1. Mechanical design and interfaces<br/>
Filter slides in detailed stages. Stuart to create a step file from the Zemax with fixed workplanes to aid referencing individual CAD assemblies.
+
<li>Filter slides in detailed stages. Stuart to create a step file from the Zemax with fixed workplanes to aid referencing individual CAD assemblies.<br/>
Kathryn to set up interactive cable/equipment list based on Coggle diagram received, detailing by all parties
+
<li>Kathryn to set up interactive cable/equipment list based on Coggle diagram received, detailing by all parties</li>
 
+
<br/>
2. Parts procurement
+
2. Parts procurement<br/>
Nikon has been received
+
<li>Nikon has been received
CCD has been ordered from Andor
+
<li>CCD has been ordered from Andor
 
+
<br/><br/>
3. Software
+
3. Software<br/>
Software working group to be formed, first meeting in the 1200 SAST time slot on 2020/03/13. Carel will invite the relevant SAAO parties.
+
<li>Software working group to be formed, first meeting in the 1200 SAST time slot on 2020/03/13. Carel will invite the relevant SAAO parties.<br />
Draft functionality requirements from SAAO side to be developed during the course of the week, for discussion Friday - Carel to distribute
+
<li>Draft functionality requirements from SAAO side to be developed during the course of the week, for discussion Friday - Carel to distribute<br/>
Draft capabilities and any interactive requirements from LJMU side to be developed (i.e. what commands and information do LJMU currently expect the instrument to issue)
+
<li>Draft capabilities and any interactive requirements from LJMU side to be developed (i.e. what commands and information do LJMU currently expect the instrument to issue)
 
+
<br/><br/>
4. Slit
+
4. Slit<br/>
SAAO to discuss slit requirements
+
<li>SAAO to discuss slit requirements<br/>
LJMU manufacture these in house, so it can be anything
+
<li>LJMU manufacture these in house, so it can be configuration<br/>
Iain distributed an example slit arrangement they have in use
+
<li>Iain distributed an example multi-width slit arrangement they have in use
 
+
[[File:slit_example_iain_20200306.png|thumbnail]]
 
+
<br/>
5. Schedule and reviews
+
5. Schedule and reviews<br/>
 +
<li>A hardware design review is required to push forward on manufacturing - target end March<br/>
 +
<li>Durations estimates from LJMU:<br/>
 +
<li>From design review ~ 2 months for hardware manufacture<br/>
 +
<li>From manufacture ~ 2 months for setup and lab testing<br/>
 +
<li>Software effort unknown at this stage<br/>
 +
<li>Area on wiki to be set up with FAT topics & prelim delivery placeholders (Kathryn)<br/>

Revision as of 15:34, 6 March 2020

1. Mechanical design and interfaces

  • Filter slides in detailed stages. Stuart to create a step file from the Zemax with fixed workplanes to aid referencing individual CAD assemblies.
  • Kathryn to set up interactive cable/equipment list based on Coggle diagram received, detailing by all parties

  • 2. Parts procurement

  • Nikon has been received
  • CCD has been ordered from Andor

    3. Software
  • Software working group to be formed, first meeting in the 1200 SAST time slot on 2020/03/13. Carel will invite the relevant SAAO parties.
  • Draft functionality requirements from SAAO side to be developed during the course of the week, for discussion Friday - Carel to distribute
  • Draft capabilities and any interactive requirements from LJMU side to be developed (i.e. what commands and information do LJMU currently expect the instrument to issue)

    4. Slit
  • SAAO to discuss slit requirements
  • LJMU manufacture these in house, so it can be configuration
  • Iain distributed an example multi-width slit arrangement they have in use
    Slit example iain 20200306.png


    5. Schedule and reviews

  • A hardware design review is required to push forward on manufacturing - target end March
  • Durations estimates from LJMU:
  • From design review ~ 2 months for hardware manufacture
  • From manufacture ~ 2 months for setup and lab testing
  • Software effort unknown at this stage
  • Area on wiki to be set up with FAT topics & prelim delivery placeholders (Kathryn)